The Night Shift

Work is progressing well at Woodmansterne WTW where the 248m³ base of the Chlorine Contact Tank was poured this week – Sean Taylor and the team on site had to work through the night to ensure the power-floated finish met the required tolerances. A great effort by all concerned!