Blackwell Hollow Bank Stabilisation

Blackwell Hollow Bank Stabilisation

Client

Sussex Police / East Grinstead Town Council

Description

Stabilisation of an 80m long steep bank above a busy road including re-profiling of the slope and soil nailing to prevent landslips

Duration

6 weeks

George Street, Croydon

George Street, Croydon

Client

London Borough of Bromley

Description

Supply and lay a mixture of natural stone paving flags and concrete block paving elements, along with stainless steel street furnishings including bins and seating benches.

Duration

20 Weeks

Crystal Palace Railway Station

Crystal Palace Railway Station

Client

London Borough of Bromley

Description

Supply and lay a mixture of natural stone paving flags to the footpath and concrete sett paving to the highway, plus stainless steel street markings.

Duration

16 Weeks

Ardingly Sewage Treatment Works

Ardingly Sewage Treatment Works

Client

Morrison Utility Services

Description

Civil works to provide flows for new wastewater treatment plant, including ducting, ductile iron pipework, reinforced concrete bases and new road and footpath construction.

Duration

24 Weeks

Goldstone Nitrate Filtration Plant

Goldstone Nitrate Filtration Plant

Client

Southern Water

Description

Works entailed the construction of reinforced concrete tanks and bases for sand filters, enclosed in a specially designed eco-friendly wood panelled building, as well as a 350mm diameter 4.5km pipeline linking the plant to nearby reservoirs.

Duration

48 Weeks

Reservoir Security Covers – Term Contract

Reservoir Security Covers – Term Contract

Client

SES Water

Description

Works comprising:

  •  Removal of existing reservoir and water tower security covers and replacement with new ‘Technocovers’ under live conditions.
  •  Specialist concrete repairs
  •  Ducting to link covers to control kiosks.
  •  Miscellaneous civils works

Duration

2001-05

Turks Retaining Wall

Turks Retaining Wall

Client

East Sussex County Council

Description

Works comprised of:

  •  Road closure and traffic management under Chapter 8
  •  CAT scan and trial holes to locate services in verge
  •  Placement of bales across stream, downstream of works to trap silt, etc disturbed by works
  •  Placement of 84 no. steel sheet piles
  •  Installation of 21 ground anchors
  •  Construction of reinforced concrete capping beam
  •  Reinstatement of eroded bank areas

Duration

8 Weeks

Church Acre Bridge

Church Acre Bridge

Client

East Sussex County Council

Description

Church Acre bridge is listed and located across one of the many drainage channels criss-crossing the Pevensey Marshes, a triple SSI site.

The bridges on the marshes were originally the responsibility of the Environment Agency but they recently passed into the care of East Sussex County Council.  The Council have instigated a programme of inspecting and repairing as necessary the many bridges on the marsh.

Church Acre bridge required extensive repairs and strengthening to the brick arch brickwork, re-pointing, and the installation of sheet pile training walls to each side of the bridge aprons.  The parapet was also increased in height to comply with present day regulations and new copings installed.  The bridge is now in a fit state for the 21st Century.

Duration

8 Weeks

Chartham Park Golf Club

Chartham Park Golf Club

Client

Transcontinental Golf Construction Ltd

Description

Earthworks and landscaping in the construction of this 18 hole golf course, including excavation of the 6 lakes and construction of the stone retaining walls, as well as sympathetic landscaping in keeping with the surrounding features.

We also carried out the construction of the access road and reinforced concrete cart paths.

Duration

48 weeks

London Golf Club

London Golf Club

Client

Transcontinental Golf Construction

Description

Excavation of 10 lakes and construction of such golf course features as tees, greens and bunkers, as well as reinforced concrete buggy paths, main access road, and the installation of the main carrier drains across the golf course.

Duration

52 Weeks